Project Portfolio Workflows
Status flows for projects, cost estimates, budgets, the quote-to-contract path, change requests, timesheets, approvals, billing, revenue true-ups and AI intake drafts, with the action that moves each record.
Project Portfolio Workflows
Every record in Project Portfolio moves through a fixed set of statuses. The server checks each move, so a page offers only the actions that are valid for the current status and for the signed-in person's permissions.
Hub: Target Document Flow. Overview: Project Portfolio. PDF: Project Portfolio Guide.
Opportunity to close
One project from plan to close
flowchart TB
Start((New project)) --> Plan[Plan the work]
Plan --> Estimate[Estimate cost]
Estimate --> Approve{Estimate approved?}
Approve -->|No| Estimate
Approve -->|Yes| Price[Price and quote]
Price --> Accepted{Customer accepts?}
Accepted -->|Order| Contract[Contract]
Accepted -->|Revise| Price
Contract --> Deliver[Deliver and log time]
Deliver --> Bill[Bill milestones and progress]
Bill --> Revenue[Recognize revenue]
Revenue --> Close[Close and learn]
class Start egkStart
class Plan,Estimate,Price egkDraft
class Approve,Accepted egkDecision
class Contract,Deliver,Bill,Revenue egkActive
class Close egkSuccess
Pages call the API at /api/v1/ppm. Invoices go through Accounts Receivable and journals through the General Ledger posting service, each with an idempotency key so a retry never posts twice.
Project lifecycle
#Stages and statuses
Stages: Opportunity, Feasibility, Planning, Costing, Commercial, Contracted, Execution, Closing, Closed, Cancelled
Statuses: Draft, Active, OnHold, Completed, Cancelled
Stage changes
flowchart TB Start((Create project)) --> Planning[Planning] Planning -->|Add estimate revision| Costing[Costing] Costing -->|Approve estimate or quote customer| Commercial[Commercial] Commercial -->|Record contract| Contracted[Contracted] Commercial -->|Quotation converted to order| Execution[Execution] Contracted -->|Start execution| Execution Planning -->|Start execution| Execution Execution -->|Begin closing| Closing[Closing] Execution -->|Close project| Closed[Closed] Closing -->|Close project| Closed Execution -->|Cancel| Cancelled[Cancelled] Closed -->|Reopen| Execution Cancelled -->|Reopen| Planning class Start egkStart class Planning,Costing egkDraft class Commercial,Contracted egkDecision class Execution,Closing egkActive class Closed egkSuccess class Cancelled egkError
| Action | Enabled when | Notes |
|---|---|---|
| Start execution | Before Execution, not on hold |
A contract is not required. The actual start date is recorded |
| Put on hold | Not on hold, not closed or cancelled | Status becomes OnHold; the stage is kept |
| Resume | OnHold |
Status returns to Active |
| Begin closing | Execution |
|
| Close project | Execution or Closing |
Blocked while change requests are open, timesheets are submitted or revenue proposals are open. Status becomes Completed |
| Cancel project | Any open stage, including on hold | Status becomes Cancelled |
| Reopen project | Closed or Cancelled |
Returns to Execution if the project ever started, otherwise Planning |
Every stage action needs Update on projects.
Automatic moves only go forward: a project that is already further along keeps its stage. The first move turns a Draft project Active. Opportunity and Feasibility are shown on the stepper as the pipeline stages before planning.
Cost estimates
#Statuses
Draft, Submitted, Approved, Rejected, Superseded
Estimate revision
flowchart TB Start((New estimate revision)) --> Draft[Draft] Draft -->|Add lines, Submit| Submitted[Submitted] Submitted -->|Approve| Approved[Approved] Submitted -->|Reject with note| Rejected[Rejected] Approved -->|A later revision is approved| Superseded[Superseded] class Start egkStart class Draft egkDraft class Submitted egkWarn class Approved egkSuccess class Rejected egkError class Superseded egkTerminal
| Action | Enabled when | Notes |
|---|---|---|
| New estimate revision | No revision is Draft or Submitted; project not closed or cancelled |
Moves the project to Costing |
| Add line | Draft |
Approved revisions cannot be edited; start a new revision |
| Submit | Draft with at least one line |
Opens approval requests by the estimate total |
| Approve | Submitted |
Freezes the costing snapshot, supersedes the earlier approved revision, moves the project to Commercial and prepares the standard pricing scenario |
| Reject | Submitted |
The note is kept; start a new revision to try again |
Budgets
#Statuses
Draft, Approved, Rejected, Superseded
Budget version
flowchart TB Start((Create from approved estimate)) --> Draft[Draft] Draft -->|Approve| Approved[Approved baseline] Draft -->|Reject| Rejected[Rejected] Approved -->|A later budget is approved| Superseded[Superseded] class Start egkStart class Draft egkDraft class Approved egkSuccess class Rejected egkError class Superseded egkTerminal
| Action | Enabled when | Notes |
|---|---|---|
| Create budget | The estimate revision is Approved and has no budget yet |
The first budget is Original, later ones Revised. Opens approval requests |
| Approve | Draft |
Becomes the earned value baseline and sets the project's approved budget |
| Reject | Draft |
From the approvals queue |
Quote to contract
From approved cost to a signed contract
flowchart TB
Snapshot((Approved costing snapshot)) --> Scenario[Pricing scenario]
Scenario --> Studio[Project Quote Studio]
Studio --> Guard{Discount within limit and price above floor?}
Guard -->|Yes| Quote[Quotation ready to send]
Guard -->|No| Wait[Waits for discount approval]
Wait -->|Approved| Quote
Quote -->|Customer accepts| Order[Convert to sales order]
Order --> Contract[Contract at net value]
Contract --> Exec[Project in Execution]
class Snapshot egkStart
class Scenario,Studio egkDraft
class Guard egkDecision
class Wait egkWarn
class Quote,Order egkActive
class Contract,Exec egkSuccess
| Step | What happens |
|---|---|
| Quote the customer | The quotation is linked to the project, the project adopts the customer and moves to Commercial |
| Convert to sales order | A contract is created once per quotation: milestone billing, value net of discounts and before tax. An execution baseline of the plan is captured and the project moves to Execution |
| Record contract by hand | For work agreed outside Sales: billing basis, value and retention. Moves the project to Contracted |
Billing is always raised from the project, never from the sales order, so the customer is invoiced once.
Change requests
#Statuses
Submitted, Approved, Rejected
Change request
flowchart TB Start((Raise change)) --> Submitted[Submitted] Submitted -->|Approve| Approved[Approved] Submitted -->|Reject with note| Rejected[Rejected] Approved --> Effects[Forecast, budget and contract updated] class Start egkStart class Submitted egkWarn class Approved egkSuccess class Rejected egkError class Effects egkActive
| Action | Enabled when | Notes |
|---|---|---|
| Raise change | Any time | Numbered CR-…, submitted at once with approval requests by the cost impact |
| Approve | Submitted |
Moves the forecast finish by the schedule days, adds the cost impact to the planned cost and approved budget, adds a change order and the price impact to the latest contract. Decided once |
| Reject | Submitted |
The note is kept |
A change cannot lower the contract value below what is already billed.
Timesheets
#Statuses
Submitted, Approved, Rejected
Weekly timesheet
flowchart TB
Start((Log the week)) --> Submitted[Submitted]
Submitted -->|Approve| Approved[Approved]
Submitted -->|Reject with reason| Rejected[Rejected]
Rejected -->|Log and submit again| Submitted
Approved --> Post{Labour posting on?}
Post -->|Yes| Journal[WIP and labour absorption journal]
Post -->|No| Actuals[Task actuals only]
class Start egkStart
class Submitted egkWarn
class Approved egkSuccess
class Rejected egkError
class Post egkDecision
class Journal,Actuals egkActive
| Rule | Detail |
|---|---|
| Entries | Each entry is above 0 and at most 24 hours, inside the week; a day cannot exceed 24 hours |
| One week | A week that is submitted or approved cannot be submitted again |
| Cost | Hours × the resource's hourly cost; overtime at 1.5× |
| Posting | One journal per company with the key PPM.Timesheet, so approval never posts twice |
Approvals
#States
Pending, Approved, Rejected
Subjects: estimates, budgets, baselines, change requests, timesheets, contracts, billing, AI drafts and quotations.
Approval request
flowchart TB
Start((Record submitted)) --> Rules{Active rule for subject and amount?}
Rules -->|Yes| Steps[One step per role in the rule]
Rules -->|No| Default[One step: Finance or Manager]
Steps --> Pending[Pending]
Default --> Pending
Pending -->|Approve| Approved[Approved]
Pending -->|Reject with note| Rejected[Rejected]
class Start egkStart
class Rules egkDecision
class Steps,Default egkDraft
class Pending egkWarn
class Approved egkSuccess
class Rejected egkError
With no matching rule, estimates, budgets and billing go to Finance and everything else to a Manager. Deciding the record closes all of its pending steps.
Billing and revenue
Billing event and revenue true-up
flowchart TB
Done((Milestone completed or progress measured)) --> Check{Contract, customer and company?}
Check -->|No| Stop[Billing refused]
Check -->|Yes| Bill[Billing event]
Bill --> Invoice[Accounts Receivable invoice less retention]
Invoice --> Earned[Earned revenue under the policy]
Earned --> Proposal[Open true-up proposal]
Proposal -->|Approve| Journal{Earned above invoiced?}
Journal -->|Yes| Unbilled[Dr unbilled receivable, Cr revenue]
Journal -->|No| Deferred[Dr revenue, Cr deferred revenue]
class Done egkStart
class Check,Journal egkDecision
class Stop egkError
class Bill,Invoice,Earned egkActive
class Proposal egkWarn
class Unbilled,Deferred egkSuccess
| Rule | Detail |
|---|---|
| Milestone billing | The milestone must be completed and is billed once |
| Headroom | A bill cannot exceed the contract value left to bill |
| Retention | The contract's retention percent is withheld from the invoice line |
| Taxes | Milestone invoices carry the taxes quoted to the customer |
| One proposal | Each contracted project keeps one open proposal; the nightly job keeps it current |
| Posting | Only the difference is posted, with the key PPM.RevRec; a proposal of zero has nothing to post |
AI intake drafts
#Statuses
Proposed, Applied, Rejected
Project intake
flowchart TB Start((Describe new demand)) --> Proposed[Proposed draft with phases] Proposed -->|Create project| Applied[Applied] Proposed -->|Reject| Rejected[Rejected] Applied --> Project[New project in Planning] class Start egkStart class Proposed egkWarn class Applied egkSuccess class Rejected egkError class Project egkActive
Applying needs the Approve permission on AI. The draft never prices, quotes or posts anything.